| SNo | UserName | TotalTask | DelayTask | 9:30-11:30 | 11:30-01:30 | 01:30-02:00 | 02:00-03:30 | 03:30-05:00 | 05:00-06:30 |
|---|---|---|---|---|---|---|---|---|---|
| Dotnet team | |||||||||
| 1 | nehal | 52 | - |
Project: Other Works
application live on ios
3 hr
28 min
|
No Task | Lunch |
Project: Other Works
dependency update in EMS application
3 hr
22 min
|
No Task | No Task |
| 2 | kapil singh | 57 | 2 |
Project: Sugarcane Monitoring
Display real estate and agriculture-related data plots on the map, including counts for real estate data.
7 hr
57 min
|
No Task | Lunch |
Project: Sugarcane Monitoring
Display real estate and agriculture-related data plots on the map, including counts for real estate data.
7 hr
57 min
|
No Task | No Task |
| 3 | Shivam Singh | 76 | - |
Project: Vahan GPS
Allow users to delete records in Master modules with confirmation popup, proper validation, and success/error notifications
5 hr
1 min
|
Project: Vahan GPS
Allow users to delete records in Master modules with confirmation popup, proper validation, and success/error notifications
5 hr
1 min
|
Lunch |
Project: Vahan GPS
Add validation logic in bulk device upload to classify records as valid/invalid and restrict wallet access for admin based on defined conditions.
3 hr
20 min
|
No Task | No Task |
| 4 | Brijendra Goswami | 44 | 1 | No Task | No Task | Lunch | No Task | No Task | No Task |
| 5 | Ashish Kumar Sharma | 69 | 4 |
Project: Vahan GPS
include Sim Profile + backend in customer plan master
3 hr
17 min
|
No Task | Lunch | No Task | No Task | No Task |
| 6 | Sandeep | 38 | - |
Project: Wave EMS
Going wave office for apply leave issue
3 hr
33 min
|
No Task | Lunch | No Task | No Task | No Task |
| 7 | Chandra Prakash | 37 | - |
Project: Vahan GPS
create api for sim profile master
3 hr
30 min
|
Project: Vahan GPS
create api for sim profile master
3 hr
30 min
|
Lunch |
Project: Vahan GPS
create api for sim profile master
3 hr
30 min
|
No Task | No Task |
| 8 | Archana Kumari | 32 | 1 |
Project: Smart Office
work on dashboard
8 hr
33 min
|
Project: Smart Office
work on dashboard
8 hr
33 min
|
Lunch |
Project: Smart Office
work on dashboard
8 hr
33 min
|
No Task | No Task |
| Opensource Team | |||||||||
| 1 | Raj | 16 | 2 | No Task | No Task | Lunch | No Task | No Task | No Task |
| 2 | Nikita | 20 | 4 | No Task | No Task | Lunch | No Task | No Task | No Task |
| 3 | vinay kumar | 35 | 8 | No Task | No Task | Lunch | No Task | No Task | No Task |
| 4 | Anku singh | 36 | 8 |
Project: aaaskyerp
CRM Implementation AAA Skyerp
7 hr
27 min
|
Project: aaaskyerp
Dropdown changes in Lead Doctype
6 hr
0 min
|
Lunch |
Project: aaaskyerp
Dropdown changes in Lead Doctype
6 hr
0 min
|
No Task | No Task |
| 5 | shruti brijpuriya | 18 | 3 | No Task | No Task | Lunch | No Task | No Task | No Task |
| Admin | |||||||||
| 1 | Manav Gupta | 24 | 8 | No Task | No Task | Lunch | No Task |
Project: LIS Cane
verifying the geojson data e got for the villages
1 hr
30 min
|
No Task |
| 2 | Shaswat Swapnil | 99 | 1 | No Task | No Task | Lunch |
Project: LIS Cane
study the image types and plan next move for GIS.
1 hr
30 min
|
No Task | No Task |
| 3 | Satyam Agrahari | 17 | 2 | No Task | No Task | Lunch | No Task | No Task | No Task |
| OELTEAM | |||||||||
| Dm Team | |||||||||
| 1 | Pratyush Tripathi | 0 | - | No Task | No Task | Lunch | No Task | No Task | No Task |
| 2 | Chemri | 0 | - | No Task | No Task | Lunch | No Task | No Task | No Task |
| 3 | Tainyu | 0 | - | No Task | No Task | Lunch | No Task | No Task | No Task |
| 4 | Muskan | 0 | - | No Task | No Task | Lunch | No Task | No Task | No Task |
| wave group | |||||||||
| 1 | chintu | 17 | 1 |
Project: Mata Bhagwanti Chadha Niketan
The assessment module allows users to create and manage assessment lists and sections dynamically, with configurable fields and options for structured assessment data management.
6 hr
46 min
|
No Task | Lunch | No Task | No Task | No Task |
| 2 | ansarali -2 | 23 | 1 |
Project: Mata Bhagwanti Chadha Niketan
1. add new item in the academic evaluation dropdown 2. Check student id in the IEP just after creating new term. 3. add filter based on term in the intervention.
7 hr
46 min
|
No Task | Lunch | No Task | No Task | No Task |
| 3 | ansar -1 | 19 | 6 |
Project: Mata Bhagwanti Chadha Niketan
1. implement api therapist 2. new tabs and ui 3. complete all process of the assessment of Receptionist
6 hr
48 min
|
Project: Mata Bhagwanti Chadha Niketan
1. implement api therapist 2. new tabs and ui 3. complete all process of the assessment of Receptionist
6 hr
48 min
|
Lunch | No Task | No Task | No Task |